Termination for cause is costly and adversarial and has been covered in this article. But can a terminating party use equipment and tools left behind on the worksite (i.e., a crane)? The answer depends on what is in your contract.
Under ConsensusDocs, a constructor must give its permission to use any equipment or supplies left at the worksite, such as a crane.[i] Moreover, the owner must indemnify the constructor for using their equipment. This makes sense because even if a constructor were appropriately terminated for cause, using their equipment and materials they no longer possess or control unfairly creates additional liability exposure. At a minimum, the owner should take on the risk of using the equipment and materials since they benefit from such use.