Government Claims Act Does Not Apply to Actions Solely Seeking Declaratory Relief and Not Monetary Relief

Fountain pen on Claim

In December 2015, general contractor Stronghold Engineering Incorporated entered into a construction contract with the City of Monterey for the renovation of the City’s conference center and an adjacent city-owned plaza.

March 25, 2024
Garret Murai - California Construction Law Blog

Perhaps it should come as no surprise, but public entities get special treatment under the law, and when filing a claim against a public entity, in most cases, a claimant is required to file a claim with the public entity before filing suit under the Government Claims Act (Gov. Code §810 et seq.).

But, as the next case demonstrates, that’s not always the case. In Stronghold Engineering Incorporated v. City of Monterey, 96 Cal.App.5th 1203 (2023), the 6th District Court of Appeals examined whether a public works contractor that alleged an extended overhead claim was required to file a Government Claims Act claim before filing suit when its initial complaint was limited to a claim for declaratory relief.

The Stronghold Case
In December 2015, general contractor Stronghold Engineering Incorporated entered into a construction contract with the City of Monterey for the renovation of the City’s conference center and an adjacent city-owned plaza. The construction contract provided that any modification to the construction contract had to be approved by the City through a written change order. No surprise there.

Mr. Murai may be contacted at gmurai@nomosllp.com



714.701.9180

Arrange No Cost Consultation










Subscribe to Construction Defect Journal

Construction Defect Journal Archives - Recent CD News for Construction Claims Professionals

 

Construction Defect Journal is aggregated from a variety of news sources, article submissions, contributors, and information from industry professionals.

No content on this site should be construed as legal advice or expert opinion. By viewing this site you agree to be bound by its terms and conditions

 

Copyright 2024 - Construction Defect Journal – All Rights Reserved