The court granted the insurer's motion for summary judgment finding damage to the gym floor due to a poor paint job was not a resulting loss. Bob Robinson Commercial Flooring, Inc. v. RLI Ins,. Co., 2023 U.S. Dist. LEXIS 196105 (D. Ark. Nov. 1, 2023).
Bob Robinson Commercial Flooring (BRCF) submitted a bid to the general contractor, Nabholz Construction Corporation, to install a vinyl athletic floor and striping at a middle school. The job also included the painting of a "Wildcat" logo the main gym floor. Therefore, BRCF's job was to install floors with proper painting and striping. Robert Liles and Robert Lines Parking Lot Services was the subcontractor hired to do the painting and striping. BRCF did not supervise or inspect Liles' work while it was ongoing.
Nabholz informed BRCF that there were problems with the floor painting, including crooked lines, incorrect markings, misplacement of the three point lines for the basketball surface, drips, smudges, etc. The gym floor was eventually rejected due to the nature of the vinyl flooring, once primer and paint were applied, the paint could not be removed and repainted. BRCF had to hire a new subcontractor to remove the flooring, install new flooring and then paint new lines. The cost for removal and replacement was $134,188.95.
Mr. Eyerly may be contacted at te@hawaiilawyer.com