Ultimately, the owner completed the project on its own, rebidding the project, and demanded its losses from the surety.
A performance bond surety for a defaulted general contractor principal found itself with a recalcitrant owner which refused to accept the tender of a replacement general contractor to complete a $3,000,000 construction project in Monmouth County, New Jersey.
Even before the original GC was off the job, the surety – having been notified of the contractor’s difficulties in performing the work – stepped in promptly, providing assistance in the form of an additional contractor. At the surety’s behest, that additional contractor remained on the project (focused principally at the time on roof repairs) after the initial GC was placed in default and terminated.
Eventually, the surety, by draft tender agreement issued to the owner, offered that the additional contractor serve as the completion contractor for the entire project (not simply the roof repairs), a proposal rejected by the owner – which had never cared for the additional contractor. Instead, the owner proposed its own completion contractor and, in connection with that offer, demanded a sum of money ($1.6 million) from the surety – a proposal the surety rejected: “[Owner] cannot choose whatever contractor it wants to complete the work and then charge the costs to [the surety]."
Mr. Lund may be contacted at daniel.lund@phelps.com